Experience a Better Way to Build

Discover how system-built homes drastically reduce construction time compared to traditional methods, delivering a faster, more efficient path to your new home.

System-Built Home

6 -8 weeks
Design & Planning
  • Customization of floor plans and features

  • Approval of designs and initial permit applications

Site-Built Home

8 - 12 weeks
Design & Planning
  • Customization of floor plans and features

  • Approval of designs and initial permit applications

8 - 12 weeks
Manufacturing the Modules
  • Factory construction of modules (walls, floors, roofs, etc.)

  • Quality inspections and assembly line efficiency

3 - 4 weeks
Site Preparation
  • Clearing and grading the land

  • Laying the foundation (basement or slab)

2 - 4 weeks
Site Preparation
  • Concurrent with manufacturing

  • Clearing and grading the land

  • Pour foundation

6 -8 weeks
Framing & Structural Work
  • Building the frame of the house

  • Installing roof trusses and sheathing

1 week
Transportation of Modules
  • Modules are transported from the factory to the site

2 - 4 weeks
Roofing & Siding
  • Installing the roof and exterior walls

  • Windows and exterior doors

1 week
Assembly on Site
  • Modules are craned into place

  • Connecting modules, dried-in.

6 -8 weeks
Rough-In Work
  • Plumbing, electrical, and HVAC installations

  • Insulation and drywall installation

8 - 12 weeks
Finishing Work
  • Exterior and interior finishes (painting, flooring, etc...)

  • Utility connections and landscaping

10 - 12 weeks
Interior & Exterior Finishing
  • Interior finishes (painting, flooring, cabinetry)

  • Exterior finishes, including landscaping

1 - 2 weeks
Final Inspections & Handover
  • Inspections by local authorities

  • Addressing any final touch-ups

  • Handover of the completed home

2 - 4 weeks
Final Inspections & Handover
  • Inspections by local authorities

  • Addressing any final touch-ups

  • Handover of the completed home

Total Duration
28 - 40 weeks
Total Duration
36 - 52 weeks

These timelines for both methods are merely approximations. They are based on average conditions and can vary depending on factors such as location, complexity, weather, and availability of materials and labor.

Efficient - Flexible - Quality

Modular construction offers a smarter, more efficient approach to building. By creating modules off-site in a controlled environment, we can speed up construction, improve cost efficiency, and maintain high standards of quality.

Speed of Construction

System-built construction can be completed faster than traditional methods, as modules are built off-site simultaneously with site preparation.

Cost Efficiency

The controlled environment of a factory can lead to reduced labor costs and minimized material waste, often resulting in overall cost savings.

Quality Control

The factory setting allows for consistent quality control and standardized processes, ensuring high-quality construction.

Weather Independence

Construction is less affected by weather delays because much of the work is done indoors, ensuring a more predictable schedule.

Enhanced Design Options

System-built construction allows for a wide range of design possibilities, including complex architectural designs that can be replicated consistently.

Improved Energy Efficiency

System-built buildings can be designed with energy-efficient systems and materials from the outset, often resulting in better insulation and lower energy costs in the long term.